The International Renewable Energy Agency (IRENA) has reported that energy generation and installation costs of concentrated solar power (CSP) projects fell sharply in 2018, down more than 40% from 2010.
IRENA analyzed multiple financial and technical parameters related to concentrated solar power projects in its latest report Renewable Power Generation Costs in 2018.
The agency has pointed out that despite being less popular compared to other renewable energy technologies, CSP holds significant promise in the future, with its costs expected to decline further.
Levelized Cost of Energy
This parameter is indicative of the lifetime costs of energy generation at net present value. The weighted average LCOE of CSP projects in 2018 was reported as 18.6¢/kWh, down 26% from 2017 and 46% lower than in 2010. IRENA calculated this figure on the basis of plant size as well as technology. Only ½ a gigawatt of CSP capacity was installed in 2018, with dominance by China, Morocco, and South Africa.
IRENA notes that the main reason behind the decline in the LCOE is improved supply chain in China, improved developer experience, and competitive auctions in the last few years.
Installed Costs
The weighted average installed cost has also declined 28% in 2018 to $5,204/kW. This is around 41% lower than the cost in 2010 and 50% lower than the cost in 2011. Apart from the inherently high costs related to CSP projects, the installed cost is also high due to the low number of project commissioned in any year. However, installed costs are expected to decline over the coming years as more projects are expected to the commissioned in China and the Middle East–North Africa (MENA) region.